Report page 75
Review of the operations of the NSW Reconstruction Authority
Review of the operations of the NSW Reconstruction Authority
Grants and funding arrangements
63
the floods in the Central West region in 2022. The Council had to borrow from its
reserves to fund recovery work during this time.416
5.72 Mr James Prosser, Senior Project Manager, Port Macquarie Hastings Council, told
the Committee that the Council cannot begin certain recovery work until it has all
necessary processes in place and funding approved, which can take years.
417 Mid
North Coast Joint Organisation also noted that most member councils still had
not received confirmation of eligibility for DRFA funding four months after the
May 2025 East Coast severe weather event. This left them uncertain about the
scope or timing of restoration funding and unable to commit to essential
recovery works.
418
5.73 The Institute of Public Works Engineers Australia (IPWEA) NSW & ACT described
the Authority's DRFA systems as 'woefully inadequate'. They contrasted the
agency's processes and the delays councils experience with the work of the
Queensland Reconstruction Authority (QRA), and said that the QRA processes
claims in as little as three weeks in certain instances.
419 However, Tim Mackney,
Board Director, IPWEA NSW & ACT also acknowledged that the Authority is in a
'teething period' and the QRA has more experience with these processes.420 The
Authority also advised they are working with the QRA to learn from them
(discussed further below).421
5.74 IPWEA noted the Authority could reduce delays by increasing staffing in DRFA
administration, as it was currently under-resourced in this area.
422
5.75 The Committee is of the view that the Authority should have funds readily
available so that councils do not incur this extra financial burden at a time when
council assets are adversely impacted. Consideration should be given to whether
the NSW Reconstruction Authority Fund, established under section 22 of the Act,
is adequately supporting the prompt distribution of funding to councils and other
organisations assisting with recovery.423
The Authority is making changes to DRFA administration
5.76 The Committee heard that the Authority is taking steps to address issues causing
delays in administering DRFA. It has announced new funding packages,
centralised DRFA administration, and investing in new software.
New funding packages
5.77 Following the May 2025 East Coast severe weather event, the NSW Government
worked with NEMA and the Australian Government to set up a $19 million
416 Submission 18, pp 4, 6.
417 James Prosser, Transcript of evidence, 17 February 2026, p 6.
418 Submission 24, pp 6-7.
419 Submission 43, p 5.
420 Tim Mackney, Transcript of evidence, 3 November 2025, p 48.
421 Andrew Graham, Transcript of evidence, 20 February 2026, p 37.
422 Institute of Public Works Engineering Australasia, Answers to supplementary questions, 3 December 2025, p 3.
423 NSW Reconstruction Authority Act 2022, s 22.